Weekly work plan re-designed
Made short movie clip for film-festival “Globale”. After some criticism 2nd version of global film clips edited and cut with voice over by volunteers
introductory lap of the new volunteer on the property
training in machetes handling with new volunteers
Bought a lot of material in Colono, transport-organization.
Receiving and unloading Cacha and Colono delivery
House area:
- Patio: Beams painted and mounted on the shower walls: bitumen tape and pre-painted beams, Pre-painting of the Melina boards with varnish. Work on the roof of the guest house, replacement of 2 roof beams, installation of zinc sheets. Beam painted for the wall next to Tank 6. Then mounted it.
- Crooked House, Gregs Room: Removal of the floor, Termite damage inspected, especially on the railing of the guest house. Finished ceiling in Double-room
- Volonteers kitchen: Inspection of the damage to the beams by Polilla. packing and removal of the industrial kitchen, cleaning of the freezer. A termite nest was removed from beneath the kitchen and burned afterwards.
- 2 deliveries of Cacha received and unloaded
- Banana plants cleaned
- Guesthouse: The roof of the guest house has been completely renewed. Started renewing working plate in kitchen. Covering Tank-wall in guesthouse with Fibrolit.
- Fire made and termite-infested timber burned.
- Room cleaning and preparation of sleeping space for new Volunteer (Ampel-room)
Compost plant: Almost every day there were stones sorted and removed. Almost every day there were 1-2 shifts made with the Hilti hammering down the concrete wall. Two Cacha beams renewed in the volunteer kitchen and another one beneath it.
Pineapple-fields cleaned. Cutting the hedge in front of this area.
Bamboo-fields: started mowing. Banana plants cleaned. Mowed and cut the grass and katuk with the machete
Old fountain fields: compost resorting, tree trimming. Cut down green waste and throw it on the compost, remove plants from bamboo
Chilamate fields: Started mowing and cleaning plants.